What happened
On Nov 25, 2026, the FCC's Space Bureau authorized SpaceX to deploy up to 1,000,000 "Starmind" satellites that will operate as data centers in orbit (FCC order DA 26-1273). The agency called it the first U.S. authorization for a constellation of data centers in space, and it denied petitions from Amazon's Kuiper Systems (Amazon Leo), Viasat and the American Astronomical Society (FCC; GeekWire).
How it actually works
Satellites go into orbital shells "each spanning 50 km at altitudes from 500 to 1,002 km," at 30-degree and sun-synchronous inclinations. SpaceX's nominal plan lists six shells, from 550–568 km up to 967–1,002 km (FCC). In general orbital-mechanics terms, which the order doesn't spell out, a sun-synchronous orbit keeps a satellite at a near-constant angle to the sun. That suits a machine that runs on solar panels.
The data link is laser, not radio. The license covers radio only for backup telemetry, tracking and command, in Ka-band (18.8–19.3 GHz down, 28.6–29.1 GHz up). It's granted on an "unprotected and non-interference basis." SpaceX told the FCC that each satellite's primary communications "will be via optical intersatellite links (ISLs) with SpaceX's Starlink constellations" (FCC). So the compute rides on Starlink's network to reach the ground.
The deadlines are steep. One satellite must be operating by Nov 25, 2033, then 10% of the authorized number by 2035, 50% by 2038 and the rest by Nov 25, 2040. If SpaceX misses them, the authorization lapses (FCC). Ten percent is 100,000 satellites. Today about 17,000 satellites exist in orbit in total, and Starlink has just over 11,000 of its own after asking for 42,000 (Al Jazeera/Reuters).
Most of the altitude band isn't cleared yet. The FCC found SpaceX's debris plan compliant only for satellites below 600 km. The grant is conditioned on SpaceX filing a modification "containing its final orbital debris mitigation plan... prior to deploying any Starmind satellites that will operate at altitudes above 600 km" (FCC). Four of the six nominal shells sit above 600 km.
Heat is the physics problem. In vacuum there's no air or water to carry heat away, so every watt the chips burn has to leave as infrared radiation from a radiator. A physics preprint posted in April 2026 sized a representative 1 MW orbital compute node. It needed about 5,640 m² of solar panels and about 2,500 m² of radiator, at 29.4 kg per kilowatt for the panels, batteries and radiators alone. With the rest of the spacecraft included, the total came to 34–59 kg/kW (Turyshev, arXiv:2604.27197). The astronomers raised the same issue from the other side. AAS argued that the constellation's "thermal signature" would raise the infrared background of the sky. The FCC ruled that concern outside its radio-frequency remit (FCC).
SpaceX said in August that each Starmind satellite "will include Nvidia Rubin GPUs and Vera CPUs" (GeekWire). The order itself names no chips and no power level per satellite.
The opportunity
SpaceX already sells compute on the ground. Its Super Intelligence segment brought in $7.6 billion of revenue in the third quarter of 2026. The company had 1.7 GW of computing capacity at the end of September and expects 2.5–3 GW by year-end (Broadband Breakfast). Proponents of solar-powered orbital data centers say they address the top concerns about terrestrial ones: land use, power consumption and water for cooling. Critics point to cooling the satellites, space traffic and orbital debris (GeekWire).
The preprint frames the test as a cost per kilowatt. A terrestrial data-center benchmark of $10,000–40,000 per kW, at about 40 kg per kW, leaves only $250–1,000 per kilogram for launch and spacecraft build combined. That allowance is 3.4–13.5 times below today's public price for a dedicated Falcon 9 launch to low Earth orbit, before the spacecraft is even built. The paper calls "space-native preprocessing and communications-integrated edge compute" the credible early regimes. It says general compute for users on the ground only closes at "low Earth-coupled communication intensity," among other conditions (Turyshev).
Others are filing too. Blue Origin has proposed 51,600 satellites, Starcloud 88,000 and Cowboy Space 20,000. Google plans to launch its first Project Suncatcher satellites no earlier than 2029, and the FCC says it is reviewing further orbital data-center proposals (GeekWire).
Maps to
How this connects
Sources
On the mechanism
- FCC Space Bureau, Memorandum Opinion and Order and Authorization, DA 26-1273 (Starmind), FCC · Nov 25, 2026
- FCC clears SpaceX to put up to a million satellites in orbit for Starmind data center network, GeekWire · Nov 25, 2026
- US grants SpaceX approval for 1 million space data centres, Al Jazeera / Reuters · Nov 25, 2026
- Orbital Data Centers: Spacecraft Constraints and Economic Viability (preprint), arXiv · Apr 29, 2026
On the opportunity
- Orbital Data Centers: Spacecraft Constraints and Economic Viability (preprint), arXiv · Apr 29, 2026
- Starlink Reaches 13.6 Million Subscribers Globally as SpaceX Revenue Jumps 161%, Broadband Breakfast · Oct 20, 2026
- FCC clears SpaceX to put up to a million satellites in orbit for Starmind data center network, GeekWire · Nov 25, 2026
Analysis and explanation only, not investment advice. Checked against every cited source by an independent verification pass before publishing. Spot an error? It gets corrected and noted here.